Canterbury Earthquakes Royal Commission Te Komihana Rūwhenua o Waitaha Canterbury Earthquakes Royal Commission – Te Komihana Rūwhenua o Waitaha

Those who lost relatives and friends in the 22 February earthquake can be assured that there will be a very thorough inquiry into the failure of buildings that resulted in loss of life.
Chair, Justice Mark Cooper
 

CTV Building Hearing - Week 6

Timetable

Date Time 

Witness 

Called by 

Nature of Evidence
30 July 10am Alun Wilkie, architect for the CTV building. Read only statement

building design 

10.20am Michael Kirkland of Saunders and Co, counsel for David Harding

 

10.45am David Harding, employed as a structural engineer by Alan Reay Consulting Engineer between 1984 and 1985. Mr Harding prepared the detailed design of the CTV building. Saunders and Co building design
11.35am BREAK
11.50am David Harding (continued)
1pm BREAK
2.15pm David Harding (continued)
3.30pm BREAK
3.50pm David Harding (continued)
5pm ADJOURNED
31 July 9.30am David Harding (continued)
11.30am BREAK
11.45am David Harding (continued)
1pm BREAK
2.15pm David Harding (continued)
2.55pm Dr Alan Reay, principal of Alan Reay Consulting Engineer, the firm that designed the CTV building. Buddle Findlay building design
3.30pm BREAK
3.45pm Dr Reay (continued)
5pm ADJOURNMENT
1 August 9.30am Dr Reay (continued)
11.30am BREAK
11.45am Dr Reay (continued)
1pm BREAK
2.15pm Dr Reay (continued)
3.45pm BREAK
4pm John Henry, structural engineer employed by Alan Reay Consulting Engineer between 1984 and 1985. Counsel assisting the Commission building design
5pm ADJOURNMENT
2 August 9.30am John Henry (continued)
11.35am BREAK
11.50am John Henry (continued)
1pm BREAK
2.15pm Patricia Tapper, widow of Graeme Tapper, who was involved in checking and issuing a building permit for the CTV building in 1986. Counsel assisting the Commission building permit
2.30pm John Henry (continued)
3.30pm BREAK
3.45pm John Henry (continued)
5.10pm ADJOURNED UNTIL 6 AUGUST