Canterbury Earthquakes Royal Commission Te Komihana Rūwhenua o Waitaha Canterbury Earthquakes Royal Commission – Te Komihana Rūwhenua o Waitaha

Those who lost relatives and friends in the 22 February earthquake can be assured that there will be a very thorough inquiry into the failure of buildings that resulted in loss of life.
Chair, Justice Mark Cooper

Document library

Document categories

Additional filter options

Choose 1 or more filters then press 'Apply filter'
Reset

Search results

Published No sorted Title Not sorted Author(s) Not sorted Category Not sorted Subject(s) Sorted descending Building(s) Not sorted Action
2011-11-03-16- 06-0303 November 2011Performance of Unreinforced Masonry Buildings in the 2010/2011 Canterbury Earthquake Swarm: Peer Review by Bret Lizundia, September 2011Performance of Unreinforced Masonry Buildings in the 2010/2011 Canterbury Earthquake Swarm: Peer Review by Bret Lizundia, September 2011
  • Lizundia, Bret
  • Rutherford & Chekene
    Technical Report
    Unreinforced Masonry Buildings (URM)
    2011-11-10-09- 57-4710 November 2011Letter from Selwyn District Council about unreinforced masonry (URM) and earthquake-prone building policiesLetter from Selwyn District Council about unreinforced masonry (URM) and earthquake-prone building policies
    • Christensen, John
    • Selwyn District Council
      RFI Response
      Unreinforced Masonry Buildings (URM)
      2011-10-27-17- 26-5327 October 2011Submission by Adam William Thornton, October 2011Submission by Adam William Thornton, October 2011
        Thornton, Adam William
        Submission
        Unreinforced Masonry Buildings (URM)
        2012-03-12-13- 11-2812 March 2012Comments on Seismicity and Building Zone Factors: Submission by Ross Thomson, September 2011Comments on Seismicity and Building Zone Factors: Submission by Ross Thomson, September 2011
          Thomson, Ross
          Submission
          Unreinforced Masonry Buildings (URM)
          2011-11-14-17- 30-2514 November 2011Photos of Buildings in Wellington: Presentation by Wellington City Council, November 2011Photos of Buildings in Wellington: Presentation by Wellington City Council, November 2011
            Wellington City Council
            Exhibit
            Unreinforced Masonry Buildings (URM)
            2011-11-10-09- 59-3610 November 2011Letter from Waimakariri District Council about unreinforced masonry (URM) and earthquake-prone building policiesLetter from Waimakariri District Council about unreinforced masonry (URM) and earthquake-prone building policies
            • Harrison, Nick
            • Waimakariri District Council
              RFI Response
              Unreinforced Masonry Buildings (URM)
              2011-10-27-16- 54-3727 October 2011Submission by International Council on Monuments and Sites ( ICOMOS) New Zealand, October 2011Submission by International Council on Monuments and Sites ( ICOMOS) New Zealand, October 2011
                Jones, Kevin
                Submission
                Unreinforced Masonry Buildings (URM)
                2011-10-27-17- 24-1927 October 2011Submission by Local Government New Zealand, October 2011Submission by Local Government New Zealand, October 2011
                  Local Government New Zealand
                  Submission
                  Unreinforced Masonry Buildings (URM)
                  2011-10-27-17- 13-3927 October 2011Submission by New Zealand Historic Places Trust, October 2011Submission by New Zealand Historic Places Trust, October 2011
                  • Jackson, Nicola
                  • New Zealand Historic Places Trust
                    Submission
                    Unreinforced Masonry Buildings (URM)
                    2012-04-05-14- 02-2405 April 2012Heritage Buildings, Earthquake Strengthening and Damage: The Canterbury Earthquakes September 2010-January 2012: Technical report by Robert McClean and NZHPTHeritage Buildings, Earthquake Strengthening and Damage: The Canterbury Earthquakes September 2010-January 2012: Technical report by Robert McClean and NZHPT
                      New Zealand Historic Places Trust
                      Technical Report
                      Unreinforced Masonry Buildings (URM)
                      2011-10-27-17- 12-0127 October 2011Submission by Auckland Council, October 2011Submission by Auckland Council, October 2011
                      • Auckland Council
                      • Reade, Patricia
                        Submission
                        Unreinforced Masonry Buildings (URM)
                        2012-02-13-11- 43-3113 February 2012Management of Earthquake Risk: Submission by Department of Building and Housing, January 2012Management of Earthquake Risk: Submission by Department of Building and Housing, January 2012
                          Department of Building and Housing
                          Submission
                          Unreinforced Masonry Buildings (URM)
                          2012-03-12-12- 53-1512 March 2012Unreinforced masonry and other earthquake-prone buildings - requirements for seismic strengthening: submission by Department of Building and Housing, October 2011Unreinforced masonry and other earthquake-prone buildings - requirements for seismic strengthening: submission by Department of Building and Housing, October 2011
                            Kelly, David
                            Submission
                            Unreinforced Masonry Buildings (URM)
                            2011-11-14-14- 32-3814 November 2011Draft Policy on Earthquake-Prone Buildings: Letter by Sir Miles Warren, ArchitectDraft Policy on Earthquake-Prone Buildings: Letter by Sir Miles Warren, Architect
                              Warren, Miles
                              Exhibit
                              Unreinforced Masonry Buildings (URM)
                              2011-10-27-17- 00-3827 October 2011Submission (A) Overview by the Standards Council, October 2011Submission (A) Overview by the Standards Council, October 2011
                                Standards Council
                                Submission
                                Unreinforced Masonry Buildings (URM)
                                2011-11-14-08- 54-2114 November 20112011-11-07 Unreinforced Masonry Buildings and Earthquake-Prone Policies hearing: transcript of Opening Statement from Stephen Mills, QC2011-11-07 Unreinforced Masonry Buildings and Earthquake-Prone Policies hearing: transcript of Opening Statement from Stephen Mills, QC
                                  Mills, Stephen
                                  Transcript
                                  Unreinforced Masonry Buildings (URM)
                                  2011-11-15-09- 17-0315 November 20112011-11-07 Unreinforced Masonry (URM) Buildings and Earthquake-Prone Policies hearing transcript2011-11-07 Unreinforced Masonry (URM) Buildings and Earthquake-Prone Policies hearing transcript
                                  • Chapman, Bruce
                                  • Ingham, Jason M
                                    Transcript
                                    Unreinforced Masonry Buildings (URM)
                                    2011-11-15-09- 08-4015 November 20112011-11-08 Unreinforced Masonry (URM) Buildings and Earthquake-Prone Policies hearing transcript2011-11-08 Unreinforced Masonry (URM) Buildings and Earthquake-Prone Policies hearing transcript
                                    • Ingham, Jason M
                                    • Lizundia, Bret
                                    • Turner, Fred
                                      Transcript
                                      Unreinforced Masonry Buildings (URM)
                                      2011-11-15-09- 07-5115 November 20112011-11-09 Unreinforced Masonry (URM) Buildings and Earthquake-Prone Policies hearing transcript2011-11-09 Unreinforced Masonry (URM) Buildings and Earthquake-Prone Policies hearing transcript
                                        Speakers - Various
                                        Transcript
                                        Unreinforced Masonry Buildings (URM)
                                        2011-11-03-16- 05-2703 November 2011The Performance of Earthquake Strengthened URM Buildings in the Christchurch CBD in the 22 February 2011 Earthquake: Addendum Report by Associate Professor Jason M. Ingham and Professor Michael C. Griffith, October 2011The Performance of Earthquake Strengthened URM Buildings in the Christchurch CBD in the 22 February 2011 Earthquake: Addendum Report by Associate Professor Jason M. Ingham and Professor Michael C. Griffith, October 2011
                                        • Griffith, Michael C
                                        • Ingham, Jason M
                                        • University of Auckland
                                          Technical Report
                                          Unreinforced Masonry Buildings (URM)

                                          Search results navigation

                                          Displaying 37 - 56 of 1689 items arrow left First arrow left Prev arrow right Next arrow right Last