Canterbury Earthquakes Royal Commission Te Komihana Rūwhenua o Waitaha Canterbury Earthquakes Royal Commission – Te Komihana Rūwhenua o Waitaha

Those who lost relatives and friends in the 22 February earthquake can be assured that there will be a very thorough inquiry into the failure of buildings that resulted in loss of life.
Chair, Justice Mark Cooper

Document library

Document categories

Additional filter options

Choose 1 or more filters then press 'Apply filter'
Reset

Search results

Published Sorted ascending Title Not sorted Author(s) Not sorted Category Not sorted Subject(s) Not sorted Building(s) Not sorted Action
2012-07-10-11- 42-0810 July 2012CTV Building hearing: NZS 4203:1984  Code of practice for general structural design and design loadings for buildings, page 63.CTV Building hearing: NZS 4203:1984  Code of practice for general structural design and design loadings for buildings, page 63.
    Standards New Zealand
    Exhibit
    Standards and Regulation
    Madras 249
2012-07-10-11- 44-5510 July 2012CTV Building hearing: Certificate of Title 31F/154 issued 14 October 1988 to Madras Street Properties LimitedCTV Building hearing: Certificate of Title 31F/154 issued 14 October 1988 to Madras Street Properties Limited
    Registrar-General of Land New Zealand
    Exhibit
    Buildings - Representative Sample
    Madras 249
2012-07-10-11- 45-2210 July 2012CTV Building hearing: CTV Building Collapse Investigation for CEBPTI Panel - draft report by Dr Clark Hyland and Ashley SmithCTV Building hearing: CTV Building Collapse Investigation for CEBPTI Panel - draft report by Dr Clark Hyland and Ashley Smith
  • Hyland Consultants Ltd
  • Hyland, Clark
  • Smith, Ashley
  • Structure Smith Consulting Engineers
    Exhibit
    Buildings - Representative Sample
    Madras 249
2012-07-10-11- 48-3910 July 2012CTV Building hearing: Email from Rob Jury to Clark Hyland regarding CTV Analyses and Collapse ScenariosCTV Building hearing: Email from Rob Jury to Clark Hyland regarding CTV Analyses and Collapse Scenarios
    Jury, Rob
    Exhibit
    Buildings - Representative Sample
    Madras 249
2012-07-10-11- 48-5110 July 2012CTV Building hearing: Email from Clark Hyland to Rob Jury and Nigel Priestley regarding CTV Analyses and Collapse ScenariosCTV Building hearing: Email from Clark Hyland to Rob Jury and Nigel Priestley regarding CTV Analyses and Collapse Scenarios
    Hyland, Clark
    Exhibit
    Buildings - Representative Sample
    Madras 249
2012-07-10-11- 59-3110 July 2012CTV Building hearing: Letter reply from David Kelly (DBH) to Buddle Findlay, regarding requests made in letter of 22 May 2012CTV Building hearing: Letter reply from David Kelly (DBH) to Buddle Findlay, regarding requests made in letter of 22 May 2012
  • Department of Building and Housing
  • Kelly, David
    Exhibit
    Buildings - Representative Sample
    Madras 249
2012-07-10-12- 00-1510 July 2012CTV Building hearing: Diagram for building, including walls, internal column support, and shear wall loadsCTV Building hearing: Diagram for building, including walls, internal column support, and shear wall loads
    Fenwick, Richard
    Exhibit
  • Buildings - Representative Sample
  • Engineering
    Madras 249
2012-07-10-12- 03-3410 July 2012CTV Building hearing: Tables from CTV Non-Linear Seismic Analysis Report, by Compusoft Engineering Limited, showing diaphragm connection forces - LytteltonCTV Building hearing: Tables from CTV Non-Linear Seismic Analysis Report, by Compusoft Engineering Limited, showing diaphragm connection forces - Lyttelton
  • Bradley, Derek
  • Compusoft Engineering
  • Stuart, Tony
    Exhibit
    Engineering
    2012-07-10-12- 06-4510 July 2012CTV Building hearing: Conclusion of draft report prepared by Dr Clark Hyland and Ashley Smith for DBHCTV Building hearing: Conclusion of draft report prepared by Dr Clark Hyland and Ashley Smith for DBH
    • Hyland Consultants Ltd
    • Hyland, Clark
    • Smith, Ashley
      Exhibit
      Buildings - Representative Sample
      Madras 249
    2012-07-10-12- 11-4510 July 2012CTV Building hearing: Minute Concerning Performance of the CTV Building CTV Building hearing: Minute Concerning Performance of the CTV Building
    • Canterbury Earthquakes Royal Commission
    • Cooper, Justice
      Exhibit
      Buildings - Representative Sample
      Madras 249
    2012-07-10-12- 13-0710 July 2012CTV Building hearing: Non Linear Time Analysis Model of CTV BuildingCTV Building hearing: Non Linear Time Analysis Model of CTV Building
    • Hyland Consultants Ltd
    • Hyland, Clark
    • Smith, Ashley
    • Structure Smith Consulting Engineers
    • Exhibit
    • Physical copy only
      Buildings - Representative Sample
      Madras 249
    2012-07-10-12- 13-4410 July 2012CTV Building hearing: Email from David Hopkins to Ashley Smith and Clark Hyland regarding Variation of Opinion List for CTV Report 120123 CTV Building hearing: Email from David Hopkins to Ashley Smith and Clark Hyland regarding Variation of Opinion List for CTV Report 120123
      Hopkins, David
      Exhibit
      Buildings - Representative Sample
      Madras 249
    2012-07-10-12- 14-0910 July 2012CTV Building hearing: Email between David Hopkins, Mike Stannard, and Sherwyn Williams regarding Clark and Ashley's reportsCTV Building hearing: Email between David Hopkins, Mike Stannard, and Sherwyn Williams regarding Clark and Ashley's reports
      Various
      Exhibit
      Buildings - Representative Sample
      Madras 249
    2012-07-10-12- 16-1210 July 2012CTV Building hearing: DBH Email between David Hopkins, Sherwyn Williams, and Richard Sharpe regarding Review of CTV ReportCTV Building hearing: DBH Email between David Hopkins, Sherwyn Williams, and Richard Sharpe regarding Review of CTV Report
      Various
      Exhibit
      Buildings - Representative Sample
      Madras 249
    2012-07-10-12- 22-3710 July 2012CTV Building hearing: GF Calculations relating to possible collapse scenarios and interior beam-column joint diagramCTV Building hearing: GF Calculations relating to possible collapse scenarios and interior beam-column joint diagram
      Various
      Exhibit
      Buildings - Representative Sample
      Madras 249
    2012-07-10-12- 25-4110 July 2012CTV Building hearing: Drawings provided by Graham Frost of interior beam/column joint and PC Beam Stress concept CTV Building hearing: Drawings provided by Graham Frost of interior beam/column joint and PC Beam Stress concept
      Frost, Graham
      Exhibit
      Buildings - Representative Sample
      Madras 249
    2012-07-10-12- 29-1110 July 2012CTV Building hearing: CTV Building Collapse Technical Investigation - presentation by Dr Clark Hyland and Ashley SmithCTV Building hearing: CTV Building Collapse Technical Investigation - presentation by Dr Clark Hyland and Ashley Smith
    • Hyland, Clark
    • Smith, Ashley
      Exhibit
    • Building assessments after earthquakes
    • Buildings - Representative Sample
    • Engineering
      Madras 249
    2012-07-10-12- 29-4110 July 2012CTV Building hearing: Minutes of meeting of Clark Hyland and Ashley Smith with USAR Engineers held in Christchurch on 29 April 2011 as part of the Christchurch Earthquake CBD Building Performance InvestigationCTV Building hearing: Minutes of meeting of Clark Hyland and Ashley Smith with USAR Engineers held in Christchurch on 29 April 2011 as part of the Christchurch Earthquake CBD Building Performance Investigation
      Smith, Ashley
      Exhibit
      Buildings - Representative Sample
      Madras 249
    2012-07-10-12- 40-1510 July 2012CTV Building hearing: Graham Frost (USAR Support Engineer's) account to DBH about his observations and opinions in relation to the CTV collapseCTV Building hearing: Graham Frost (USAR Support Engineer's) account to DBH about his observations and opinions in relation to the CTV collapse
      Frost, Graham
      Exhibit
      Buildings - Representative Sample
      Madras 249
    2012-07-10-15- 32-1610 July 2012CTV Building hearing: Email from David Hopkins to Clark Hyland, Ashley Smith, and Sherwyn Williams regarding Comments on ARCL ResponsesCTV Building hearing: Email from David Hopkins to Clark Hyland, Ashley Smith, and Sherwyn Williams regarding Comments on ARCL Responses
      Various
      Exhibit
      Buildings - Representative Sample
      Madras 249

    Search results navigation

    Displaying 849 - 868 of 1327 Items arrow left First arrow left Prev arrow right Next arrow right Last