Canterbury Earthquakes Royal Commission Te Komihana Rūwhenua o Waitaha Canterbury Earthquakes Royal Commission – Te Komihana Rūwhenua o Waitaha

Those who lost relatives and friends in the 22 February earthquake can be assured that there will be a very thorough inquiry into the failure of buildings that resulted in loss of life.
Chair, Justice Mark Cooper

Document library

Document categories

Additional filter options

Choose 1 or more filters then press 'Apply filter'
Reset

Search results

Published No sorted Title Not sorted Author(s) Sorted ascending Category Not sorted Subject(s) Not sorted Building(s) Not sorted Action
2011-10-28-10- 44-4028 October 2011Scientific Understanding of the Canterbury Crustal Earthquakes from 4 September 2010 to their Closure on 21 June 2011 - Addendum: Submission by James Quinwallace, September 2011Scientific Understanding of the Canterbury Crustal Earthquakes from 4 September 2010 to their Closure on 21 June 2011 - Addendum: Submission by James Quinwallace, September 2011
    Quinwallace, James
    Submission
    Seismicity
    2011-10-28-10- 43-0328 October 2011Scientific Understanding of the Canterbury Crustal Earthquakes from 4 September 2010 to their Closure on 21 June 2011: Submission by James Quinwallace, September 2011Scientific Understanding of the Canterbury Crustal Earthquakes from 4 September 2010 to their Closure on 21 June 2011: Submission by James Quinwallace, September 2011
      Quinwallace, James
      Submission
      Seismicity
      2011-10-28-10- 47-3128 October 2011Submission by Rachael Ford and Ed Radley, September 2011Submission by Rachael Ford and Ed Radley, September 2011
        Radley, Ed
        Submission
        Seismicity
        2012-02-02-15- 44-2302 February 2012Colombo 603 and 605-613 hearing: Brief of Evidence of Anthony Francis RaperColombo 603 and 605-613 hearing: Brief of Evidence of Anthony Francis Raper
          Raper, Anthony Francis
          Exhibit
          Buildings - Representative Sample
          Colombo 605
        2012-09-06-16- 40-1906 September 2012CTV Building hearing: Photographs of building interior taken on levels 2-5 by Leonard Pagan, Quantity Surveyor for Rawlinsons, as part of a building inspection on 29 September 2010CTV Building hearing: Photographs of building interior taken on levels 2-5 by Leonard Pagan, Quantity Surveyor for Rawlinsons, as part of a building inspection on 29 September 2010
          Rawlinsons Ltd
          Referenced Document
          Buildings - Representative Sample
          Madras 249
        2012-06-28-12- 36-3028 June 2012CTV Building hearing: Photographs of the building interior taken 29 September 2010CTV Building hearing: Photographs of the building interior taken 29 September 2010
          Rawlinsons Ltd
          Exhibit
          Buildings - Representative Sample
          Madras 249
        2012-11-26-15- 40-5326 November 2012CTV Building hearing: Email exchange between the Royal Commission and Richard Raymond with a query regarding shear wallsCTV Building hearing: Email exchange between the Royal Commission and Richard Raymond with a query regarding shear walls
          Raymond, Richard
          Exhibit
          Buildings - Representative Sample
          Madras 249
        2011-10-27-17- 12-0127 October 2011Submission by Auckland Council, October 2011Submission by Auckland Council, October 2011
          Reade, Patricia
          Submission
        • Building assessments after earthquakes
        • Placarding (Stickering)
        • Safety Evaluation
        • Seismic Strengthening
        • Standards and Regulation
        • Unreinforced Masonry Buildings (URM)
          2012-11-22-17- 06-1522 November 2012CTV Building hearing - Letter dated 24 February 2012 from Alan Reay to David Hopkins of DBH regarding the final reportCTV Building hearing - Letter dated 24 February 2012 from Alan Reay to David Hopkins of DBH regarding the final report
            Reay, Alan
            Exhibit
            Buildings - Representative Sample
            Madras 249
          2012-08-01-16- 08-3201 August 2012CTV Building hearing: Second Statement of Evidence of Alan Michael ReayCTV Building hearing: Second Statement of Evidence of Alan Michael Reay
            Reay, Alan
            Exhibit
            Buildings - Representative Sample
            Madras 249
          2012-08-01-16- 22-3301 August 2012CTV Building hearing: Timesheet for work at Alan Reay Consulting Ltd in 1986 CTV Building hearing: Timesheet for work at Alan Reay Consulting Ltd in 1986
            Reay, Alan
            Exhibit
            Buildings - Representative Sample
            Madras 249
          2012-09-06-16- 17-4406 September 2012CTV Building hearing: Schedule – Summary of ARCE time records for Job 2503. CTV Building hearing: Schedule – Summary of ARCE time records for Job 2503.
            Reay, Alan
            Referenced Document
            Buildings - Representative Sample
            Madras 249
          2012-11-22-16- 04-2422 November 2012 CTV Building hearing - Madras 249 CTV Building - Letter dated 3 May 2011 from Alan Reay of Alan Reay Consultants Ltd to Clark Hyland of Hyland Fatigue and Earthquake Engineering CTV Building hearing - Madras 249 CTV Building - Letter dated 3 May 2011 from Alan Reay of Alan Reay Consultants Ltd to Clark Hyland of Hyland Fatigue and Earthquake Engineering
            Reay, Alan
            Exhibit
            Buildings - Representative Sample
            Madras 249
          2012-08-01-16- 09-0101 August 2012CTV Building hearing: Composite Statements of Evidence of Alan Michael Reay - Design IssuesCTV Building hearing: Composite Statements of Evidence of Alan Michael Reay - Design Issues
            Reay, Alan
            Exhibit
            Buildings - Representative Sample
            Madras 249
          2012-08-07-16- 58-5907 August 2012CTV Building hearing: Composite statement of evidence of Alan Reay - Permit issues CTV Building hearing: Composite statement of evidence of Alan Reay - Permit issues
            Reay, Alan
            Exhibit
          • Buildings - Representative Sample
          • Engineering
            2012-08-17-16- 28-4517 August 2012CTV Building hearing: Composite Statement of Evidence of Alan Reay - Holmes Report and Retrofit IssuesCTV Building hearing: Composite Statement of Evidence of Alan Reay - Holmes Report and Retrofit Issues
              Reay, Alan
              Exhibit
            • Buildings - Representative Sample
            • Engineering
              Madras 249
            2012-11-22-16- 49-5222 November 2012CTV Building hearing - Letter from Alan Reay to Clark Hyland dated 21 April 2011confirming information request.CTV Building hearing - Letter from Alan Reay to Clark Hyland dated 21 April 2011confirming information request.
              Reay, Alan
              Exhibit
            • Buildings - Representative Sample
            • Geotechnical
            • Structural Performance
              Madras 249
            2012-11-22-16- 57-3622 November 2012CTV Building hearing - Email dated 3 February 2012 from David Hopkins of DBH to Alan Reay regarding the release of the CTV reportCTV Building hearing - Email dated 3 February 2012 from David Hopkins of DBH to Alan Reay regarding the release of the CTV report
              Reay, Alan
              Exhibit
              Buildings - Representative Sample
              Madras 249
            2012-11-26-15- 14-3326 November 2012CTV Building hearing - Handwriting sample of Alan ReayCTV Building hearing - Handwriting sample of Alan Reay
              Reay, Alan
              Exhibit
              Buildings - Representative Sample
              Madras 249
            2012-07-13-09- 53-2713 July 2012CTV Building hearing: Combined statements of evidence of Dr Alan ReayCTV Building hearing: Combined statements of evidence of Dr Alan Reay
              Reay, Alan
              Exhibit
              Buildings - Representative Sample
              Madras 249

            Search results navigation